1.2 MW wind power project of Nirmal B. Thakkar H.U.F. at Gujarat, India
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 14
Standardised Baselines N/A
Estimated annual reductions* 2,443
Start date of first crediting period. 01 Jan 10
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 12 Sep 09 - 11 Oct 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (698 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1.	Whether project meets sustainability indicators set by Indian DNA?
2.	Why plastic raw material making company interested in wind based power plant without any prior experience or exposure?
3.	How many skilled/unskilled people from surrounding area were employed at this project during construction and operation? 
4.	Environment Impact Assessment for such projects is not required as per legal requirements. But what would be impact of negative environmental conditions on project? Whether assessment of environmental conditions on project has been carried out?
5.	Please give details of stakeholders such as name, location, designation etc.
6.	Minutes of stakeholder meeting is not included in PDD.
7.	Whether local villagers would be beneficiary of CDM revenue earned by company? Any plan has been develop to earmark certain fund from CDM revenue for community welfare to improve social well being of local people?
From
Hiral Mehta/Mahesh Pandya
Environmental Engineers
Paryavaran mitra
502, Raj Avenue, Bhaikakanagar road
Thaltej, Ahmedabad - 380059
Telefax - 079-26851321/1801

Submitted by: paryavaranmitra


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs