Rishiganga Hydroelectric Project (RGHEP), India
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 53,358
Start date of first crediting period. 01 Sep 10
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 10 Jun 10 - 09 Jul 10
PP(s) for which DOE have a contractual obligation Rishi Ganga Power Corporation Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1358 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs