Waste Heat Recovery CDM Project at Attock Cement Pakistan Ltd.
[]
Host party(ies) Pakistan
Methodology(ies) AMS-III.Q. ver. 3
Standardised Baselines N/A
Estimated annual reductions* 37,908
Start date of first crediting period. 01 Sep 11
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 29 Jan 11 - 27 Feb 11
PP(s) for which DOE have a contractual obligation Attock Cement Pakistan Ltd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1194 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs