Huasahuasi I and II Hydroelectric Power Plant
[]
Host party(ies) Peru
Methodology(ies) ACM0002 ver. 11
Standardised Baselines N/A
Estimated annual reductions* 60,613
Start date of first crediting period. 01 Jul 12
Length of first crediting period. 7 years
DOE/AE AENOR INTERNACIONAL, S.A.U.
Period for comments 08 Apr 10 - 07 May 10
PP(s) for which DOE have a contractual obligation Endesa Carbono S.L.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (748 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs