Huaneng Fanshi Shanglangjian (Shahe Phase I) 49.5 MW Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 86,054
Start date of first crediting period. 01 Oct 12
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 28 Feb 12 - 28 Mar 12
PP(s) for which DOE have a contractual obligation Gazprom Marketing & Trading Singapore Pte. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1014 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Interim Rules on Economic Assessment of Electrical Engineering Retrofit Projects is not applicable to wind projects in benchmark IRR selection. Benchmark of pre-tax project IRR is 5% (Table 2.13-1) and post-tax equity IRR is 8% (Table 2.13-2) for wind projects as indicated in Economic Evaluation Methods and Parameters for Construction Projects (3rd Edition), jointly issued by NDRC and Ministry of Construction on July 3, 2006. This document is the compilation basis of financial analysis for wind projects, which is widely used in China (http://www.hydrocost.org.cn/costSoftware/windsoftware.jsp).

According to National Taxation Law, a) the first 3 years are exempted from income tax, half in the fourth to sixth year; b) VAT refund for equipment investment; c) half VAT payment.

Approved total dynamic investment is 438,790,000 CNY (http://webcache.googleusercontent.com/search?hl=zh-CN&gbv=2&gs_l=hp.3...2329l2329l0l3094l1l1l0l0l0l0l62l62l1l1l0.frgbld.&q=cache:7ZaYD_tfU_cJ:http://www.shanxigov.cn/n16/n1398/n2108/n5731/n7614959/15892494.html+%E5%8D%8E%E8%83%BD%E6%96%B0%E8%83%BD%E6%BA%90%E8%82%A1%E4%BB%BD%E6%9C%89%E9%99%90%E5%85%AC%E5%8F%B8%E7%B9%81%E5%B3%99%E5%8E%BF%E4%B8%8A%E7%8B%BC%E6%B6%A7%EF%BC%88%E7%A0%82%E6%B2%B3%E4%B8%80%E6%9C%9F%EF%BC%8949.5%E5%85%86%E7%93%A6%E9%A3%8E%E7%94%B5%E9%A1%B9%E7%9B%AE%E9%80%9A%E8%BF%87%E6%A0%B8%E5%87%86&ct=clnk)
Submitted by: fengdian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs