Myagri Bio-organic Plant at TDM Kemaman Palm Oil Mill
[]
Host party(ies) Malaysia
Methodology(ies) AMS-III.F. ver. 10
Standardised Baselines N/A
Estimated annual reductions* 34,682
Start date of first crediting period. 01 Dec 12
Length of first crediting period. 10 years
DOE/AE TUEV-RHEIN
Period for comments 03 Feb 12 - 03 Mar 12
PP(s) for which DOE have a contractual obligation Myagri Nutribio Sdn. Bhd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (831 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
This project requires a leakage assessment due to the general guidelines for SSC activities where biomass is used for Type III activities. 

The once in 3 years calibration for the oxygen analyzer is not reasonable as these analyzers drift constantly and especially the zero shift needs checking to provide reasonable analyses.
Submitted by: gerald hamaliuk


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs