Wuzhou Hydropower Project of Dao County, Yongzhou City, Hunan Province, P.R.China
[]
Host party(ies) China
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 44,986
Start date of first crediting period. 01 Apr 11
Length of first crediting period. 7 years
DOE/AE TÜV SÜD South Asia Private Limited
Period for comments 18 Aug 10 - 16 Sep 10
PP(s) for which DOE have a contractual obligation ECO Asset Incorporated.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (9006 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
There is no information of the project design, development and implementation in PDD. Furthermore, there is no sufficient information why the project is additional. Thus it concerns the CDM requirement will be achieved later by any documents supporting the argumentation.
Submitted by: shuidian


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs