Waste Heat Recovery and Power Generation Project in Yatai Group Harbin Cemennt Co., Ltd.
[]
Host party(ies) China
Methodology(ies) ACM0012 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 132,665
Start date of first crediting period. 01 Jan 10
Length of first crediting period. 10 years
DOE/AE JCI
Period for comments 16 Jun 09 - 15 Jul 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (762 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
By my knowledge, the normal annual operation hours for cement WHR in China is above 7000 hours. 
Submitted by: vincent zhang


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs