10 MW Biomass based Power plant in Punjab,India
[]
Host party(ies) India
Methodology(ies) AMS-I.C. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 57,399
Start date of first crediting period. 01 Aug 10
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 10 Jul 10 - 08 Aug 10
PP(s) for which DOE have a contractual obligation SEL Manufacturing Company Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (476 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs