6MW bundled Wind Power Project in Rajkot and Kutch districts of Gujarat
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 10,485
Start date of first crediting period. 01 Jun 11
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 26 Jan 11 - 24 Feb 11
PP(s) for which DOE have a contractual obligation The Kutch Salt & Allied Industries Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (715 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1.	If Suzlon is going to operate WEG on behalf of proponents, any agreement has been done for that?
2.	Gautam Freight has also proposed one of similar kind of wind based power plant for CDM purpose in near by area.
3.	If these much WEG are in same area (same villages and coordinates), does it put pressure on land or surrounding area in terms of noise or other disturbance?
4.	In case of failure of project or any other accident, who would be responsible for it? Suzlon or proponents?
5.	What would be impact of negative environmental conditions of area upon project? What would be alternatives in that case?
6.	How many skilled/unskilled people from surrounding area were employed at this project during commissioning and operation as mentioned in social well being section? 
7.	List of stakeholders and minutes of stakeholder meeting is not attached with PDD. If stakeholder meeting were done in 2009, why it take so long for validation?

From
Hiral Mehta/Mahesh Pandya
Environmental Engineers
Paryavaran mitra
502, Raj Avenue, Bhaikakanagar road
Thaltej, Ahmedabad – 380059 India
Telefax - 079-26851321/1801

Submitted by: paryavaranmitra

1.	Non de-bundling nature of the project is not justified properly in the section A.4.5. DOE has to validate whether there is no registered project with the PP nor there is an application for registration of any project. PP doesn’t confirm in the PDD that there is no application for registration.
2.	The date of investment decision is not provided transparently. It should be used generously in the PDD for clarity.
3.	Purchase order date mentioned in chronology of events and start date of the project activity based on purchase order date mentioned in Section C is not matching. Pls. clarify.  
4.	PP does not speak about PLF, conservative also not discussed, what values they took for calculation DOE has to give clarification and justification. 
5.	Derating factor, array efficiency of the wind energy system is not depicted in the PDD. Pls. clarify. 
6.	Debt/Equity ratio should be based on recent investment done by the Project proponent. 
7.	The calculation of project IRR is not as per “Guidance on the Assessment of Investment Analysis’ Version 03, EB 51, Annex 58”.
8.	The emission factor value for calculating baseline emission is wrong. Refer B.6.3
9.	Net electricity should be continuously monitored, hourly measured and at least monthly recorded. Refer B.7.1
10.	Metering regulations as per CEA norms is not adequately followed in monitoring plan. Refer B.7.2.

Submitted by: nancy johan


The comment period is over.