8.45 MW bundled wind energy project in Gujarat
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 15,791
Start date of first crediting period. 15 Jun 10
Length of first crediting period. 10 years
DOE/AE RINA Services S.p.A.
Period for comments 19 Dec 09 - 17 Jan 10
PP(s) for which DOE have a contractual obligation Mahalaxmi Rubtech Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1014 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Dear Project Proponent,

As i went through your Project's PDD i found out some of the projects in the bundled project are having IRR around 1.24% and even with CDM they having IRR around 4%. why do you need to set up this project if it is totally a unviable option. infact all the projects in your bundled project  are not touching the benchmark you established by even small margin. my opinion why to set up such projects.
Submitted by: Arnab deb

Comments regarding 8.45 MW bundled wind energy project in Gujarat 

1.	From which state departments NOC has been obtained for this project?
2.	For wind based power project, how land acquisition was done? If it is on temporary basis, for how many years lease has been signed? How compensation has been calculated and paid? What was type of land?
3.	Please give details of stakeholders such as name, location etc
4.	Environment Impact Assessment for such projects is not required as per legal requirements. But what would be impact of negative environmental conditions on project? Whether assessment of environmental conditions on project has been carried out as it is in earthquake zone on seashore?
5.	Whether local villagers would be beneficiary of CDM revenue earned by company? Any plan has been develop to earmark certain fund from CDM revenue for community welfare to improve social well being of local people?
6.	How many skilled/unskilled people from surrounding area were/are employed at this project during construction and operation? 
7.	Mahalaxmi group of companies is already awaiting issuance request for its renewable biomass based thermal energy generation project. Why it is interested in wind energy generation project? 

From
Hiral Mehta/Mahesh Pandya
Environmental Engineers
Paryavaran Mitra
502, Raj Avenue, Bhaikakanagar road
Thaltej, Ahmedabad - 380059
Telefax - 079-26851321/1801
Email - paryavaranmitra@yahoo.com
Submitted by: paryavaranmitra


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs