Proposed 4.2 MW wind power project
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 7,645
Start date of first crediting period. 01 Apr 13
Length of first crediting period. 7 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 05 Aug 11 - 03 Sep 11
PP(s) for which DOE have a contractual obligation Vikram Traders
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (3138 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The PLF of the project activity is nowhere mentioned in the PDD and how is the PLF justified?
Submitted by: dwarakaa

The cost of equity of 19% is very high. PDD does not give what is the duration considered for computing beta and what is the return interval selected, why BSE 500 has been selected for market return, what is the cut off date selected for beta computation etc. PDD attempts to teach the global stakeholders instead of giving information and thereby conceals the information. It is not clear how the DOE allowed the PP to web host this project unless DOE itself is not aware of the CDM methodology. KERC has recommended a post tax return of only 16%. Moreover, how does it compare with default return given by EB? The return cannot exceed whatever EB has suggested. 

KERC has recommended PLF of 26.5% for wind projects in the state after an exhaustive study. Then what is the PP/consultant talking about 22.7%?  Even that too one has to compute from sec. B.6. Besides the fact that PDD is not transparent and conceals information, the PLF of 22.7% is very low. DOE should not accept PLF less than 26.5% recommended by KERC. It should check the PLF achieved by this project.

Along with this project another project “4.2 MW Wind Power Project by National Enterprises at Tamil Nadu, India” is also webhosted, which is also based on 2.1 MW suzlon windmills. The order for this project was placed on 27/08/2010 while order was placed by Vikram Traders on 04/10/2010, just two months apart. The PDD does not disclose the offer letter date. Anyway, a comparison of these two projects will reveal that the cost is Rs.98 lakhs higher and the O&M cost is Rs.2 lakhs higher (21 lakhs in the case of National Enterprises and 21 and 24 lakhs yielding 22.5 lakhs on an average for Vikram Traders) in the case of Vikram Traders. While the annual escalation considered by National Enterprises is 5%, Vikram Traders has considered 10%. This is an illustration of what will happen if the reliance is placed on offer letters, which the PP advocates citing guidance 6 of Annex 5, EB 68 and DOE accepts the PP /consultant’s argument.  It is doubtful whether the DOE reads the VVM fully and use their sectoral and local expertise and financial knowledge. This project, is one such example. For DOE, this should indicate that they should not go by offer letter but by purchase order duly checked. 

The purchase order is issued in October. Therefore the project must have started operation in 2010-11 itself. The cash generation during 2010-11 should be deducted from the capital cost and net cost should be taken for calculating IRR.  

This project is eligible for 100% depreciation and tax holiday for first 10 years. The project developer will also save tax due to depreciation. It is not clear whether this is taken into account at all.   



Submitted by: Karthikeyan


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs