Nanti Hydro Electric Power Project in Himachal Pradesh, India
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 42,386
Start date of first crediting period. 01 Apr 14
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 02 Mar 11 - 31 Mar 11
PP(s) for which DOE have a contractual obligation Nanti Hydro Power Private Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (594 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
> DOE Should validate how the PP has used a pre tax benchmark of RBI PLR against a post tax return.
> DOE should validate how the subsidy availed by the project from MNRE is being used in the cash flow. whether the Subsidy is shown as a cash inflow of the project, as in that case the cashflow and IRR would increase simultaneously.
> 
Submitted by: Arnab deb

> DOE Should validate how the PP has used a pre tax benchmark of RBI PLR against a post tax return.
> DOE should validate how the subsidy availed by the project from MNRE is being used in the cash flow. whether the Subsidy is shown as a cash inflow of the project, as in that case the cashflow and IRR would increase simultaneously.
> 
Submitted by: Arnab deb

How  post tax is comparable to pretax benchmark rate?
Submitted by: S B

How  post tax IRR is comparable to pretax benchmark rate?
Submitted by: S B


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs