1MW Hwaseong PV (photovoltaic) Power Plant
[]
Host party(ies) Republic of Korea
Methodology(ies) AMS-I.D. ver. 12
Standardised Baselines N/A
Estimated annual reductions* 832
Start date of first crediting period. 01 Jan 08
Length of first crediting period. 10 years
DOE/AE BSI
Period for comments 11 Dec 07 - 09 Jan 08
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (703 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs