Bundled fuel switchover from coal to Natural gas project through GSPC Gas Company Limited, India
[]
Host party(ies) India
Methodology(ies) ACM0009 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 84,724
Start date of first crediting period. 01 Apr 12
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 17 Nov 11 - 16 Dec 11
PP(s) for which DOE have a contractual obligation GSPC Gas Company Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (651 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Gujarat fourm on CDM respectfully submit the following comments on the Project Design Document (PDD) for Bundle fuel switchover from coal to natural gas project through GSPC gas Company Limited in Gujarat, India. We thank the CDM Executive Board and Designated Operation Entity (DOE) for recognizing the integral role of transparency in CDM Validation process, and for taking this comment into consideration.
The project is not appropriate for the following points

o	The investment analysis is incomplete and fails to provide the data and assumptions necessary for reader to reproduce the result.

o	No commitment has been shown by the company regarding sustainable development as well as additionality as per CDM requirement.

o	No information has been provided regarding the cost of fuel switch in the PDD?


o	The direct and indirect employments have been considered as  the indicators for the Social and economical well being, but no data has been given regarding the no. of additional direct and indirect  employments will be created and no of person days will be created during the project period. 

o	The Internal Rate of Return analysis in not done and no justifications were given regarding non viability of project in absence of Clean Development Machanism.


o	In the stakeholder comments, adequate information has not been provided such as how many people have participated and how many people from near by villages have participated.

Gujarat fourm on CDM
Email: gujaratfourmoncdm@gmail.com

Submitted by: Gujarat Forum on CDM


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs