Grid connected 3MWp Solar PV power plant at Raichur District of Karnataka State, India
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 4,099
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 7 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 08 Oct 11 - 06 Nov 11
PP(s) for which DOE have a contractual obligation Karnataka Power Corporation Limited (KPCL)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (248 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs