Natural Gas based grid connected Combined Cycle Power Plant
[]
Host party(ies) India
Methodology(ies) AM0029 ver. 3
Standardised Baselines N/A
Estimated annual reductions* 118,351
Start date of first crediting period. 01 Jul 10
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 13 Jan 10 - 11 Feb 10
PP(s) for which DOE have a contractual obligation North Delhi Power Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (540 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment (62 KB) Submitted by: Guido Sabatini


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs