Green Power Asia Pte. Ltd. – Fuji Oil (S) Pte. Ltd. Cogeneration Project
[]
Host party(ies) Singapore
Methodology(ies) AMS-III.B. ver. 16
AMS-II.D. ver. 12
Standardised Baselines N/A
Estimated annual reductions* 27,615
Start date of first crediting period. 01 Jun 13
Length of first crediting period. 10 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 16 Nov 12 - 15 Dec 12
PP(s) for which DOE have a contractual obligation Green Power Asia Pte. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (4343 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
1. Table 16 for the timeline states that the start of commercial operation is on the 9th of June 2011. Whereas the project participant has stated that there is an investment barrier in section B.5 that they were unable to receive commercial financing for the project. Thus it is not clear that there is a lack of access to capital as the project activity is already fully operational.

2. In section B.5 for the prevailing practice barrier, the project activity states that it is the first of its kind but does not employ the tool for usage. This tool is also not listed as being used.

3. It is stated on page 44 that the medium pressure boilers are on hot standby. This would mean that they are constantly consuming fuel. This should be included as a project emission.

4. As the project activity is a new facility, according to the latest version of AMS II D, version 12, paragraph 8, it should be “the most plausible baseline scenario for the project activity shall be evaluated based on the related and relevant requirements in the general guidelines for SSC methodologies.” The Project Design Document does not appear to follow these guidelines.

5. Measure 1 on page 13 of the PDD describes the efficiency of Singapore’s grid. This should not be limited to the efficiency of the large scale power generation plants in Singapore but should be as an overall efficiency of the whole system. To use it as a comparison of the small scale co-generation system directly linked at the project site is not equal in magnitude.

6. Reading the information presented in the project design document, the project participant has stated this is a new facility which will be replacing the medium pressure boilers by the co-generation system. Thus, the boilers should no longer be present in the project scenario as it is stated to be replaced. The project participant should be clear on the baseline scenario and the project scenario.
Submitted by: Thirumal


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs