Bundled Renewable Power Project by EKI Energy Services Limited (EKIESL-CDM.February-15-04)
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 18
Standardised Baselines N/A
Estimated annual reductions* 18,851
Proposed start date of PA 05 Jan 12
Start date of first crediting period. 31 Dec 15
Length of first crediting period. 7 years
DOE/AE LGAI Technological Center, S.A.
Period for comments 16 Jun 15 - 15 Jul 15 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation EKI Energy Services Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (596 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs