Xuanen County Shuangxi Hydropower Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 45,434
Start date of first crediting period. 01 Oct 12
Length of first crediting period. 7 years
DOE/AE RINA Services S.p.A.
Period for comments 20 Dec 11 - 18 Jan 12
PP(s) for which DOE have a contractual obligation Electrade S.p.A.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (701 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
xuanenshuangxi@126.com

the information provided in PDD is not real and inconsistent with the real implementation of the project,

e.g. 

1) the project started construction in year 2004 as per the website information published by the local government Development and Reform Commission (DRC) of Enshi Autonomous Prefecture for Tujia & Miao Nationalities (http://www.esfg.gov.cn/html/touzi_xiangmu/zhongdian_xiangmu/07_6_22_9_15_KIF0_04B6B45999HKA12.shtml)




2) the project signed construciton contract and other contracts before 2007 and prior to the project starting date indicated in PDD. The evidence for the determination of the starting date may be forged to conform the CDM requirement. DOE shall assess the starting date through the third party evidence, especially for the main equipment purchase contract, DOE shall interview directly with the signed manufacturer to assess the reality of the contract.




3) the electricity tariff applied in PDD is not consistent with the value in project design report (FSR/PDR).




the project includes two hydropower plants. PDD hides the information and demonstrate only one.




the commmon practice analysis hides many hdyroopower projects. DOE shall request the PP to provide a valid sources for the information of hydropower plants in local area and province. and for each of the identified project, DOE shall assess the information independently through a third party evidence
Submitted by: harry

xuanenshuangxi@126.com

the information provided in PDD is not real and inconsistent with the real implementation of the project,

e.g. 

1) the project started construction in year 2004 as per the website information published by the local government Development and Reform Commission (DRC) of Enshi Autonomous Prefecture for Tujia & Miao Nationalities (http://www.esfg.gov.cn/html/touzi_xiangmu/zhongdian_xiangmu/07_6_22_9_15_KIF0_04B6B45999HKA12.shtml)




2) the project signed construciton contract and other contracts before 2007 and prior to the project starting date indicated in PDD. The evidence for the determination of the starting date may be forged to conform the CDM requirement. DOE shall assess the starting date through the third party evidence, especially for the main equipment purchase contract, DOE shall interview directly with the signed manufacturer to assess the reality of the contract.




3) the electricity tariff applied in PDD is not consistent with the value in project design report (FSR/PDR).




the project includes two hydropower plants. PDD hides the information and demonstrate only one.




the commmon practice analysis hides many hdyroopower projects. DOE shall request the PP to provide a valid sources for the information of hydropower plants in local area and province. and for each of the identified project, DOE shall assess the information independently through a third party evidence
Submitted by: harry

xuanenshuangxi@126.com


the information provided in PDD is not real and inconsistent with the real implementation of the project,

e.g. 

1) the project started construction in year 2004 as per the website information published by the local government Development and Reform Commission (DRC) of Enshi Autonomous Prefecture for Tujia & Miao Nationalities (http://www.esfg.gov.cn/html/touzi_xiangmu/zhongdian_xiangmu/07_6_22_9_15_KIF0_04B6B45999HKA12.shtml)




2) the project signed construciton contract and other contracts before 2007 and prior to the project starting date indicated in PDD. The evidence for the determination of the starting date may be forged to conform the CDM requirement. DOE shall assess the starting date through the third party evidence, especially for the main equipment purchase contract, DOE shall interview directly with the signed manufacturer to assess the reality of the contract.




3) the electricity tariff applied in PDD is not consistent with the value in project design report (FSR/PDR).




the project includes two hydropower plants. PDD hides the information and demonstrate only one.




the commmon practice analysis hides many hdyroopower projects. DOE shall request the PP to provide a valid sources for the information of hydropower plants in local area and province. and for each of the identified project, DOE shall assess the information independently through a third party evidence
Submitted by: harry


The comment period is over.