iHOT – VI water heating service
[]
Host party(ies) India
Methodology(ies) AMS-I.C. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 28,894
Start date of first crediting period. 01 Jan 11
Length of first crediting period. 7 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 15 Sep 10 - 14 Oct 10
PP(s) for which DOE have a contractual obligation RWE Power Aktiengesellschaft
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1346 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
(Page 16 of PDD for 200 LPD system)
- not clear whether the charges of 0.05 paisa per litre applies for first 2000 litres in a month or in a year.
- considering it to be conservative at 2000/month, the total unbilled amount could be 24,000 litres and the remaining 34400 litres (58400-24000), will be billed at 0.05 paisa per litre. Thus, this will yield a revenue of ~ 1720 INR per year.
- there is a fixed charge of INR 160 per month, this will yield 1920 INR per year.
- interest revenue @ 12% (equal to the lending rate considered for the project) on security deposit = INR 456 
- thus the total revenue will be 1720+1920+456 = 4096 INR per year (conservative estimate, will increase depending upon the usage).

Now considering the investment for 200 LPD unit by the PP, which is INR 26,000. 
I consider that this is the market selling rate of this unit in the open market by this company. However, sine this project is directly developed by the company, this may not be the right const to be considered for the return calculation purpose, considering the fact that the manufacturer tends have good margins in the selling of any equipments upto (30-40% including the margins of distributors/supply chain). Therefore, considering the real cost of the 200 LPD system as INR 18200 (70% of the market selling cost).
- I am little doubtful if there is big maintenance cost involved in the yearly operations in the initial years, still considering a bulk long term maintenance cost of INR 500 per unit, the net yearly revenue for the PP will be 3596 (4096-500) for a investment of INR 18200! i.e., a annual return of around 19.75% regularly for 20 years! 
- above is the simple analysis made for the project in the absence of the details provided in the PDD.
- The above calculation does not consider any subsidy component normally provided by MNRE, DOE should investigate by them self into it without asking the PP/consultant to reply since it is their job to investigate and analyse. This may further reduce the invested capital cost by the PP.
- further, the DOE is also suppose to check in case the PP is provided with any preferred loan rate, say by IREDA/MNRE, which usually do for promoting the Solar water heater in the country.
- No doubt the business model is appreciable and the project really require additional CDM revenue  for implementation.
- Tuv-NORD is validating few other similar projects and this comment applies to all other similar projects validated by the DOE.
Submitted by: Sonika


The comment period is over.