IOI Sandakan Biomass Power Plant
[]
Host party(ies) Malaysia
Methodology(ies) ACM0018
Standardised Baselines N/A
Estimated annual reductions* 155,723
Start date of first crediting period. 01 Apr 12
Length of first crediting period. 7 years
DOE/AE Bureau Veritas India Pvt. Ltd.
Period for comments 03 Nov 11 - 02 Dec 11
PP(s) for which DOE have a contractual obligation GenPower Carbon Solutions, L.P.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1505 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs