RPSL Biomass Power Plant in Jambi, Indonesia
[]
Host party(ies) Indonesia
Methodology(ies) ACM0006 ver. 12
Standardised Baselines N/A
Estimated annual reductions* 141,534
Start date of first crediting period. 01 Nov 13
Length of first crediting period. 10 years
DOE/AE SIRIM
Period for comments 21 Sep 12 - 20 Oct 12
PP(s) for which DOE have a contractual obligation PT. Rimba Palma Sejahtera Lestari
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (286 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:

The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs