Hebei Qiuxian Biomass Power Plant Project
[]
Host party(ies) China
Methodology(ies) ACM0018
Standardised Baselines N/A
Estimated annual reductions* 146,240
Start date of first crediting period. 01 Jul 12
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 28 Dec 11 - 26 Jan 12
PP(s) for which DOE have a contractual obligation UK DS Energy Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (987 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
This is a cogeneration project using cotton stalks, wheat straw, corn stalks, tree limb, etc. as biomass fuels, referring http://www.weihuagroup.com/news_view.asp?newsid=105; http://www.hbdrc.gov.cn/article.jsp?code=41/2011-03402&channelID=1_3_3
Submitted by: jia.wan


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs