20 MW Solar Project in Sanwreej, Jodhpur, Rajasthan
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 17
Standardised Baselines N/A
Estimated annual reductions* 35,149
Proposed start date of PA 20 Jul 16
Start date of first crediting period. 31 Mar 17
Length of first crediting period. 7 years
DOE/AE LGAI Technological Center, S.A.
Period for comments 16 Nov 16 - 15 Dec 16 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation Janardan Wind Energy Pvt. Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (968 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs