Small Hydro Power Plants in Braço do Norte River Bundled Project Activities (hereafter referred to simply as “SHPPs in Braço do Norte River”).
[]
Host party(ies) Brazil
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 11,399
Start date of first crediting period. 01 Jan 12
Length of first crediting period. 7 years
DOE/AE RINA Services S.p.A.
Period for comments 23 Jul 11 - 21 Aug 11
PP(s) for which DOE have a contractual obligation Geradora de Energia Nova Fátima S.A.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (630 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs