Hebei Guyuan County Dongxinying 199.5 MW Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 7
Standardised Baselines N/A
Estimated annual reductions* 428,269
Start date of first crediting period. 01 Oct 09
Length of first crediting period. 7 years
DOE/AE TUEV-RHEIN
Period for comments 13 Nov 08 - 12 Dec 08
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (501 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs