Methane Recovery and Utilization at Prosper Palm Oil Mill, Malaysia
[]
Host party(ies) Malaysia
Methodology(ies) AMS-III.H. ver. 16
Standardised Baselines N/A
Estimated annual reductions* 27,342
Start date of first crediting period. 01 Sep 12
Length of first crediting period. 10 years
DOE/AE SIRIM
Period for comments 28 Jan 12 - 26 Feb 12
PP(s) for which DOE have a contractual obligation Green Lagoon Technology Sdn Bhd
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (1016 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
On page 6 of the PDD, where does 85% efficiency derive from? Page 16, the options for use of the biogas must be evaluated and financial parameters used to measure options, even if the mill uses the gas, as stated in the Methodology additionality section. Page 19 does not mention a 10 day Measurement Campaign or using the 0.89 conservativeness factor in the calculations, and the efficiency in the data table uses 98.38%, but the data for the COD removal from the anerobic portion of the WWT system shows low 60% removal efficiency. Page 27, statement is made that for incomplete combustion in the flare, the GWP for methane is not considered - why is this?
Submitted by: gerald hamaliuk


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs