16.5 MW Grid-connected, Bundled Wind Power Project, Jodhpur, Rajasthan, India.
[]
Host party(ies) India
Methodology(ies) ACM0002 ver. 10
Standardised Baselines N/A
Estimated annual reductions* 28,268
Start date of first crediting period. 11 Jul 10
Length of first crediting period. 10 years
DOE/AE TÜV NORD CERT GmbH
Period for comments 21 Jan 10 - 19 Feb 10
PP(s) for which DOE have a contractual obligation Terapanth Foods Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (534 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs