Liaoning Kangping Zhangjiayao Wind Power Project
[]
Host party(ies) China
Methodology(ies) ACM0002 ver. 11
Standardised Baselines N/A
Estimated annual reductions* 106,912
Start date of first crediting period. 01 Jul 11
Length of first crediting period. 7 years
DOE/AE DNV-CUK
Period for comments 09 Sep 10 - 08 Oct 10
PP(s) for which DOE have a contractual obligation Longyuan Kangping Wind Power Co., Ltd.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (824 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The revenue from CDM is not clearly addressed to the stakeholders
Submitted by: goshagarwal


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs