10 MW Biomass based grid connected power generation project by Rake Power Limited at Ramtek, Nagpur.
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 13
Standardised Baselines N/A
Estimated annual reductions* 39,677
Start date of first crediting period. 01 Oct 09
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 31 Jul 09 - 29 Aug 09
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (498 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
Comment (47 KB) submitted by: Sonika on behalf of EcoSol


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs