Conversion to Natural Gas at the Salina Cruz Refinery
[]
Host party(ies) Mexico
Methodology(ies) ACM0009 ver. 4
Standardised Baselines N/A
Estimated annual reductions* 1,138,192
Start date of first crediting period. 01 Jul 13
Length of first crediting period. 10 years
DOE/AE DNV-CUK
Period for comments 15 Nov 12 - 14 Dec 12
PP(s) for which DOE have a contractual obligation Platinum Partners Value Arbitrage Fund, L.P
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (7434 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs