49.5MWp Solar Power Plant under Dohwa Le Thuy Renewable Energy Complex in Quang Binh province, Viet Nam
[]
Host party(ies) Viet Nam
Methodology(ies) ACM0002 ver. 20
Standardised Baselines N/A
Estimated annual reductions* 58,424
Proposed start date of PA 19 Jun 20
Start date of first crediting period. 01 Jan 21
Length of first crediting period. 10 years
DOE/AE 4K Earth Science Private Limited
Period for comments 14 Nov 20 - 13 Dec 20 (23:59:59 GMT)
PP(s) for which DOE have a contractual obligation Econetwork Inc.
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (844 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE
The comment period is over.
No comments received.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs