Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 5521 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Waste Heat Recovery and Utilization for Power Generation at Lucky Cement Limited, Karachi Plant |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) 1.The DOE shall further substantiate the suitability of input values used in the investment analysis, in particular: a)Cost of baseline fuel (NG,HFO,diesel) used in the IRR calculation as there is no information provided in the VR. The DOE is requested to provide the details on the how it validated the same based on objective evidence . b)the appropriateness of the methods in determining the escalation rates given that the escalation rate of the O&M costs and overhaul cost is based on historical data (page 36 of the validation report) whereas the escalation rates of the baseline fuel prices are based on future anticipation (page 38 of the validation report); (ii) the source of the yearly inflation rates in the website of inflationdata.com (row 15 of table "Basic Info_AEO06" in spreadsheet "5521_Enclosure.xls") used in calculating the escalation rates of baseline fuel prices is not specified. c) The DOE is also requested to clarify whether these yearly inflation rates are applicable to the baseline fuels in Pakistan; . Please refer to paragraph 111 (a) and (b) of VVM version 1.2.. 2) The DOE shall clarify how it validated the project to be applicable under A.M.S III-Q version 4 which states that "A facility that is existing on the starting date of the project activity (see definition in paragraph 67 of the EB 41 meeting report) as per footnote 1 of the methodology given that Kiln G started operation in January 2009 which is after the start date of the project is May 2008. Please refer to Footnote 1,AMS III-Q version 04.. 3) The DOE is requested to clarify how it validated the baseline emissions as per Footnote 1 of AMS III-Q ver 4 which states that “all options for demonstrating the use of waste energy in the absence of a CDM project activity shall be based on historic information and not on a hypothetical scenario” given that the baseline emissions for the kilns is not based on historical data but is a hypothetical figure based on design capacity. Please refer to footnote 1 of AMS III-Q version 04. The PDD and the VR states that Kiln E,F and G has a clinker production capacity of 3300 Tons per Day (TPD) whereas all excel worksheet calculations refer to the capacity as 3000 Tons per Day (TPD). Please refer to Footnote 1 ,AMS III-Q version 04.. |
|
Date | 21 Jan 13 |