Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4810 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | “Usina Interlagos Cogeneration Project” |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further validate that there are no cost savings resulting from the steam and electricity supplied from the project activity to the sugar mill or other costs savings related to the implementation of the “reference plant”. In doing so please refer to the VVM version 1.2, paragraph 111. 2. The DOE shall further validate the net electricity generated by the project activity to be exported to the grid, the plant load factor and the electricity considered as auxiliary consumption as per paragraph 111 of the VVM version 1.2 and EB 48, Annex 11. 3. The DOE is requested to clarify how the energy demand, in the absence of the project activity, met. In doing so the DOE shall further validate the total thermal and electrical energy demand sugar mill operating at full capacity in line with ACM0006, version 10. 4. The DOE is requested to clarify how it has validated that the “reference plant” using 21bar able to meet the thermal and electrical energy demand of the sugar mill operating at full addition, the DOE is requested to further validate how the project activity complies requirements of the scenario 4 of the methodology ACM0006, version 10, in particular that type and quantity of biomass residues should be used by the project and reference plants. |
|
Date | 08 Aug 11 |