Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3560 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Hunan Dongkou Small-scale Hydropower Bundled Project of China |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further explain how it has validated the O&M cost in line with the VVM version 01.2 paragraph 111 b., as: (a) it is not clear how the DOE has validated the other components of the O&M cost for each plant, such as repair fee, water fee, and material fee and other cost; (b) the O&M costs of the 5th, 6th, 7th and 8th plants are higher than the others without any justification provided; (iii) particularly, for the 6th plant, it is not clear why power plant with such small capacity requires 19 staffs, more than plants that have higher capacity. 2. The DOE is requested to further substantiate how the proposed tariff for the project activity has been considered suitable as with the application of the highest tariff issued for similar projects in the province, the IRRs of the 1st, 2nd, 3rd, 5th, 6th and 8th plants cross the benchmark. 3. The DOE is requested to further substantiate how it has validated the investment barrier in line with the EB50 Annex 13 in particular paragraphs 4 and 9, as the information regarding the nature of the company, organization and its ownership, financial information has not been provided, and as it is not clear whether the financing of the project was assured due to the benefit of the CDM. |
|
Date | 02 Jul 11 |