Project: 3529 Sichuan Miyi Chengnan 15MW Hydropower Project - Issuance Request
Project 3529: Sichuan Miyi Chengnan 15MW Hydropower Project
 
ISSUANCE STATUS Issued (on 11 Apr 13)   completeness check: complete | info & rep check: concluded
Monitoring period 27 Dec 11 - 26 Nov 12
Monitoring report Monitoring report (136 KB)
 
Request for issuance Signed form (73 KB)
Amount of CERs CERs issued up to 31 December 2012: 54,149
Serial Range: Block start: CN-5-794444632-1-1-0-3529     Block end: CN-5-794498780-1-1-0-3529
Verification and certification reports VVS/VVM version: VVS 2.0
Certification report (51 KB)
Verification report (482 KB)
Additional documents 3529_3rd_Monitoring Report (229 KB)
3529_3rd_ER sheet (30 KB)