09:10 28 Apr 25
Project:
3400 Gas-Steam Combined Cycle Power Plant (CCPP) Project of Laiwu Iron & Steel Group Corp.
- Issuance Request
Project | 3400: Gas-Steam Combined Cycle Power Plant (CCPP) Project of Laiwu Iron & Steel Group Corp. |
---|---|
ISSUANCE STATUS | Issued (on 19 Aug 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 02 Mar 12 - 27 Dec 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
265,723
Serial Range:
Block start: CN-5-842267258-1-1-0-3400
Block end: CN-5-842532980-1-1-0-3400
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: