Project:
3195 Shaqu Coal mine CMM to power generation Phase 2 Project
- Issuance Request
Project | 3195: Shaqu Coal mine CMM to power generation Phase 2 Project |
---|---|
ISSUANCE STATUS | Issued (on 10 Jan 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 03 Sep 11 - 31 Dec 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
57,401
Serial Range:
Block start: CN-5-713309931-1-1-0-3195
Block end: CN-5-713367331-1-1-0-3195
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
![]() ![]() |
Additional documents |
![]() ![]() |