Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3195 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Shaqu Coal mine CMM to power generation Phase 2 Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further substantiate how it validated the benchmark of 10%, as the observed benchmark for power sector in China is 8%, in line with VVM v1.1 paragraph 111. 2. The DOE is requested to further substantiate: a) the suitability of the O&M cost as it only crosschecked one component of the cost (water); and b) the suitability of the electricity tariff as it is not clear whether it considered the tariff subsidy of 0.25RMB/kWh, applicable to power generated from CMM. In doing so, please refer to VVM v1.1 paragraph 112 c. 3. The DOE is requested to confirm if all applicable government subsidies have been considered such as tax exemptions (income tax holiday) in line with VVM v1.1 paragraph 112 c. 4. The DOE is requested to further explain how it validated the continuation of CMM venting to be appropriate as the baseline scenario considering the enforcement of the national regulation to utilise CMM from January 2010 (Emission Standard of Coalbed Methane/Coal Mine Gas, 2008). In doing so please refer to VVM v1.1 paragraph 83 and ACM 0008 v6, page 6. 5. The DOE shall further justify the elimination of alternative scenario to utilise CMM for additional heat supply in line with ACM0008 v6, pages 7-8. In doing so, specifically indicate the prohibitive barriers or apply investment comparison. |
|