Project:
3193 Wayang Windu Phase 2 Geothermal Power Project
- Crediting Period Renewal Request
[]
Project |
3193: Wayang Windu Phase 2 Geothermal Power Project
- project design document (4183 KB) PDD appendices Appendix 1 - CER sheet star energy 12022019 (2027 KB) - crediting period renewal form (295 KB) |
---|---|
Methodologies Used |
ACM0002 ver. 19 -
Grid-connected electricity generation from renewable sources
|
VVS Version | VVS-PA 2.0 |
Standardized baselines used | N/A |
Amount of Reductions | 698,448 metric tonnes CO2 equivalent per annum |
Validation Opinion | Validation opinion (1258 KB) |
Renewal Date | (Renewable) Rejected (view history) completeness check: complete info & rep check: concluded |
Crediting Period (requested for renewal) |
02 Dec 17 - 01 Dec 24
Other crediting period(s): 02 Dec 10 - 01 Dec 17 02 Dec 17 - 01 Dec 24 |