03:00 04 Jul 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3097 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Sichuan Songxin 20MW Hydropower Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to further substantiate how the proposed tariff for the project activity has been considered suitable, as with the application of the highest tariff issued in accordance with EB 54 paragraph 53 for the similar projects in the province the project IRR crosses the benchmark. 2. The DOE is requested to further substantiate common practice analysis, as the essential distinctions between the project activity and the other similar hydro projects identified have not been sufficiently substantiated in accordance with VVM paragraph 118. |
|
Date | 26 Oct 10 |