05:33 23 May 25
Project:
2866 Bailongjiang Shuiboxia Hydropower Station
- Issuance Request
Project | 2866: Bailongjiang Shuiboxia Hydropower Station |
---|---|
ISSUANCE STATUS | Issued (on 30 May 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 30 Dec 13 - 29 Dec 14 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
181,154
Serial Range:
Block start: CN-5-977458562-2-2-0-2866
Block end: CN-5-977639715-2-2-0-2866
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: