00:47 04 Jun 23
Project:
2840 Datong River Tianwanggou Hydropower Station
- Issuance Request
Project | 2840: Datong River Tianwanggou Hydropower Station |
---|---|
ISSUANCE STATUS | Issued (on 17 Jun 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 28 Nov 13 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
168,380
Serial Range:
Block start: CN-5-882211559-2-2-0-2840
Block end: CN-5-882379938-2-2-0-2840
|
Verification and certification reports |
VVS/VVM version:
VVS 5.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: