Project: 2840 Datong River Tianwanggou Hydropower Station - Issuance Request
Project 2840: Datong River Tianwanggou Hydropower Station
 
ISSUANCE STATUS Issued (on 17 Jun 14)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 28 Nov 13
Monitoring report Monitoring report (129 KB)
 
Request for issuance Signed form (410 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 168,380
Serial Range: Block start: CN-5-882211559-2-2-0-2840     Block end: CN-5-882379938-2-2-0-2840
Verification and certification reports VVS/VVM version: VVS 5.0
Certification report (2031 KB)
Verification report (2031 KB)
Additional documents Final_ER calculations_264 Tianwanggou hydro_v02_05-03-2014 (22 KB)
Final_Monitoring Report_264 Tianwanggou hydro_v03_18-03-2014 (173 KB)