Project: 2840 Datong River Tianwanggou Hydropower Station - Issuance Request
Project 2840: Datong River Tianwanggou Hydropower Station
 
ISSUANCE STATUS Issued (on 06 May 13)   completeness check: complete | info & rep check: concluded
Monitoring period 29 Sep 11 - 31 Dec 12
Monitoring report Monitoring report (160 KB)
 
Request for issuance Signed form (263 KB)
Amount of CERs CERs issued up to 31 December 2012: 256,208
Serial Range: Block start: CN-5-810218893-1-1-0-2840     Block end: CN-5-810475100-1-1-0-2840
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (22 KB)
Verification report (288 KB)
Additional documents Revised_Monitoring_Report_Tianwanggou_Ref.2840 (130 KB)
ER_calculation_sheet_Tianwanggou_Ref.2840-2 (63 KB)