02:54 08 Jun 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2671 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Xiangfan Huaxin Cement 7.5MW Waste Heat Recovery as Power Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE shall further substantiate: (i) the suitability of the input values to the investment analysis in line with the EB 38 paragraph 54(c), in particular, O & M cost, depreciation, and amortization; and (ii) why demand/capacity charge, if it has been paid in the baseline scenario by the project participant, has not been considered as savings in the investment analysis. 2. The PP/DOE shall further substantiate that the waste heat utilized in the project activity was released into the atmosphere in the absence of the project activity at existing facility with detailed information in line with the applicability criteria of the methodology. 3. The means of calculation of fcap is not in accordance with AMS.III.Q. v1. The DOE should have raised a Corrective Action Request to require the project participant to apply AMS.III.Q. v2 or requested a deviation. As no deviation has been requested, the PP should now apply AMS.III.Q. v2 fully to this project activity. The DOE should revalidate the project applying AMS.III.Q. v2 |
|
Date | 09 Sep 09 |