2574 Guizhou Kaiyang Zijiang Hydropower Station Project
- Issuance Request
Project | 2574: Guizhou Kaiyang Zijiang Hydropower Station Project |
---|---|
ISSUANCE STATUS | Issued (on 20 Oct 11) completeness check: complete | info & rep check: concluded |
Monitoring period | 23 Sep 09 - 31 Dec 10 |
Monitoring report | Monitoring report (194 KB) |
Request for issuance | Signed form (103 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
12,130
Serial Range:
Block start: CN-5-437965597-1-1-0-2574
Block end: CN-5-437977726-1-1-0-2574
|
Verification and certification reports |
Certification report (71 KB)
Verification report (284 KB) |
Additional documents |
ER sheet Ver. 2.0 (42 KB)
MR ver. 2.0 (140 KB) |