Project: 2563 Jilin Liaoyuan 50MW Level Biomass Cogeneration Project - Issuance Request
Project 2563: Jilin Liaoyuan 50MW Level Biomass Cogeneration Project
 
ISSUANCE STATUS Issued (on 13 Nov 12)   completeness check: complete | info & rep check: concluded
Monitoring period 25 Dec 10 - 24 Mar 12
Monitoring report Monitoring report (277 KB)
 
Request for issuance Signed form (120 KB)
Amount of CERs CERs issued up to 31 December 2012: 167,180
Serial Range: Block start: CN-5-639926267-1-1-0-2563     Block end: CN-5-640093446-1-1-0-2563
Verification and certification reports VVS/VVM version: VVM 1.2
Certification report (18 KB)
Verification report (418 KB)
Additional documents ER Calculation_Liaoyuan Biomass_Ref.2563-2.xls (73 KB)
Revised Monitoring Report_Liaoyuan_Biomass_Ref.2563-2.pdf (304 KB)