20:11 27 Dec 24
Project:
2561 Heilongjiang Wangkui 50MW Level Biomass Cogeneration Project
- Issuance Request
Project | 2561: Heilongjiang Wangkui 50MW Level Biomass Cogeneration Project |
---|---|
ISSUANCE STATUS | Issued (on 17 Feb 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 02 Nov 09 - 28 Feb 11 |
Monitoring report | Monitoring report (333 KB) |
Request for issuance | Signed form (85 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
191,822
Serial Range:
Block start: CN-5-516763906-1-1-0-2561
Block end: CN-5-516955727-1-1-0-2561
|
Verification and certification reports |
Certification report (84 KB)
Verification report (915 KB) |
Additional documents |
ER_Wangkui biomass_Ref.2561-1.xls (93 KB)
MR_Wangkui Biomass_Ref.2561-1.pdf (378 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: