09:24 28 Apr 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2209 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Dalian Tuchengzi Wind Power Project 30 MW |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Further clarification is required on how the DOE has validated the appropriateness of additional costs in line with the requirements of EB 38 paragraph 54(b), as the first PDD for GSC (1 December 2007) considered a higher IRR and did not considered the supplementary FSR (elaborated in August 2007). 2. The DOE is requested to further clarify the suitability of the input values to the investment analysis as per the requirements of EB 38 paragraph 54(c) guidance, including further explanation of the reported values of annual electricity generation and electricity supply to grid. |
|
Date | 02 Feb 09 |